Short-time scheduling

 0    16 词汇卡    dklekowski
下载mp3 打印 检查自己
 
问题 English 答案 English
Types of short-term scheduling
开始学习
Forward scheduling and backward scheduling
Forward scheduling
开始学习
begins the schedule as soon as the requirements are known; often builds up WIP; jobs performed to customer order, schedule can be accomplished even if due date is missed
Backward Scheduling
开始学习
begins with the due date of the final operation, schedules jobs in reverse order, used in many manufacturing environments; ex. catering
Goals of short-term scheduling
开始学习
minimize completion time, maximise utilisation, minimise WIP inventory, minimise customer wait time
process-focused work centres
开始学习
high variety, low volume, mate-to-order, different materials and processing for each product, complex production planning and control, production scheduling aspects
Loading Jobs in Work Centres
开始学习
assigning jobs to work centres; approaches: input-output control, Gantt charts, assignment method
Input-output control
开始学习
CONWIP - constant WIP; for given average output rate, try to keep L low and constant then W will be short and constant; Little's formula
Gantt Load chart
开始学习
shows relative workload in facility, negatives: does not account for unexpected events, must be updated regularly
Assignment Method
开始学习
occurs in many environments: resources-jobs, planes-gates, course-rooms); type of binary linear programming model
Priority rules for Dispatching Jobs (sequencing)
开始学习
FCFS, EDD, SPT, LPT, CR
FCFS
开始学习
First come first serve; the first job to arrive at a work centre is processed first
EDD
开始学习
earliest due date; the job with the easiest due date is processed first
SPT
开始学习
shortest processing time first
LPT
开始学习
longets processing time first
CR
开始学习
critical ratio; the ratio of time remaining to required work time remaining is calculated and jobs are schedules in order of increasing ratio; CR = time remaining/work days remaining -> process jobs with the smallest CR first
Criteria to evaluate priority rules
开始学习
Average Completion Time= Sum of flow times / # jobs; Utilisation = Sum process time / sum flow time; Average number of jobs in system Sum Flow time /Sum processing time; average jobs lateness = sum late times / number of jobs