Project Management 1

 0    24 词汇卡    karolina323
下载mp3 打印 检查自己
 
问题 English 答案 English
project management
开始学习
the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
project management process
开始学习
Initiating, Planning, Executing, Monitoring and Controlling, Closing
Project definition
开始学习
temporary effort to create an unique product or service; critical to the business strategy
Characteristic of a project
(every project is)
开始学习
temporary & unique
Project is temporary because
开始学习
different from other ongoing operations in an organization, because unlike operations, projects have a definite beginning and an end
Project is unique
开始学习
involve one or more elements that have not been done in the past, and are therefore unique
TRIPLE CONSTRAINTS
Balancing the competing project constraints to:
开始学习
scope, budget, schedule, quality, resources, risks
Project management office (PMO)
开始学习
defines and maintains standards for project management within the organization, PMO is the source of documentation, guidance and metrics
PMO functions
开始学习
Supportive & consultative role (documentation, providers), Human resources (acquiring employees, development, training), Controlling (risk, monitoring, changes), Portfolio management (standardisation, methodology)
Work Breakdown Structure (WBS)
开始学习
Hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Work Breakdown Structure - function
开始学习
Organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement
Work Breakdown Structure - process
开始学习
Proces: subdividing project deliverables and project work into smaller, more manageable components
Work Breakdown Structure - Key benefit
开始学习
it provides a structured vision of what has to be delivered
Predecessor (WBS)
WBS DEPENDENCIES
开始学习
activity is an activity that logically comes before a dependent activity in a schedule
Successor (WBS)
WBS DEPENDENCIES
开始学习
activity is a dependent activity that logically comes after another activity in a schedule
Finish-to-start (FS)
WBS DEPENDENCIES Examples
开始学习
A logical relationship in which a successor activity cannot start until a predecessor activity has finished. Example: The awards ceremony (successor) cannot start until the race (predecessor) has finished.
Finish-to-finish (FF)
WBS DEPENDENCIES Examples
开始学习
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. Example: Writing a document (predecessor) is required to finish before editing the document (successor) can finish.
Start-to-start (SS)
WBS DEPENDENCIES Examples
开始学习
A logical relationship in which a successor activity cannot start until a predecessor activity has started. Example: Level concrete (successor) cannot begin until pour foundation (predecessor) begins.
Start-to-finish (SF)
WBS DEPENDENCIES Examples
开始学习
A logical relationship in which a successor activity cannot finish until a predecessor activity has started. Example: The first security guard shift (successor) cannot finish until the second security guard shift (predecessor) starts.
Non finacial motivation
开始学习
a day off, language course, a hand shake with boss
results indicators
开始学习
eg. written feedback
source of the data
开始学习
eg. list of participants
delegating best practices
开始学习
Delegate resources as well as work. Develop good relationships with your staff. Delegate work to employees who have the ability to do it well. Don't abandon the work. Summary.
micromanagement
开始学习
is a management style whereby a manager closely observes and/or controls and/or reminds the work of his/her subordinates or employees